What is the minimum calculated branch circuit load for 1-8 kW electric cooktop and 2-4 kW electric wall-mounted ovens installed in a dwelling unit?

Get ready for the Limited Licensed Electrician exam with our interactive quiz. Use flashcards and multiple choice questions, complete with hints and explanations for thorough preparation. Ace your test!

To determine the minimum calculated branch circuit load for an electric cooktop and wall-mounted ovens in a dwelling unit, the National Electrical Code (NEC) provides specific guidelines regarding the demand calculations for these appliances.

For a cooktop rated between 1 to 8 kW, the maximum demand is typically taken at 8 kW. This means the full load of 8 kW is used in calculations. For electric ovens, especially in this range of 2 to 4 kW each, the NEC allows for reduced demand calculations. When installing two ovens, this generally means that the highest-rated oven (4 kW) plus a fraction of the load of the second oven needs to be considered.

When performing the calculations, you would add the 8 kW from the cooktop to the demand for the ovens. The demand for both ovens involves taking the maximum rated oven and adding a percentage of the lower-rated oven. Assuming a demand factor, you might arrive at a combined total that aligns with 9.6 kW, which accounts for efficient usage and demand reduction.

Thus, the minimum calculated branch circuit load for the given appliances together combines to a total of 9.6 kW, which aligns with the specifications outlined in the